La. Admin. Code tit. 33 § III-305

Current through Register Vol. 50, No. 6, June 20, 2024
Section III-305 - Construction and Operation
A. No operation of any source or activity addressed by a regulatory permit shall commence until the appropriate permit fee has been paid and the administrative authority has notified the applicant that the application (i.e., notification form) submitted in accordance with LAC 33:III.303.H has been determined to be complete.
B. Construction of any source addressed by a regulatory permit may be prohibited by the terms of that regulatory permit until such time as the appropriate permit fee has been paid and the administrative authority has notified the applicant that the application (i.e., notification form) submitted in accordance with LAC 33:III.303.H is complete.

La. Admin. Code tit. 33, § III-305

Promulgated by the Department of Environmental Quality, Office of the Secretary, Legal Affairs Division, LR 35:457 (March 2009).
AUTHORITY NOTE: Promulgated in accordance with R.S. 30:2054.