La. Admin. Code tit. 13 § I-563

Current through Register Vol. 50, No. 11, November 20, 2024
Section I-563 - [Effective until 4/20/2025] Effective Date of Contract; Project Completion Report
A. The owner of a new manufacturing establishment or addition shall document the beginning date of operations and the date that construction is substantially complete. The owner must file that information with the department on the prescribed project completion report form not later than 90 days after the beginning of operations, completion of construction, or receipt of the fully executed contract, whichever occurs last. A project completion report fee of $250 shall be submitted with the form. The deadline for filing the project completion report may be extended pursuant to §551
B. The effective date of tax exemption contracts for property located in parishes other than Orleans Parish shall be December 31 of the year in which effective operation began or construction was essentially completed, whichever occurs first. The effective date of tax exemption contracts for property located in Orleans Parish shall be July 31 of the applicable year.

La. Admin. Code tit. 13, § I-563

Promulgated by the State Board of Commerce and Industry and the Department of Economic Development, LR 50, exp. 10/21/2024 (Emergency), Promulgated by the Board of Commerce and Industry and the Louisiana Economic Development, LR 51, exp. 4/20/2025 (Emergency).
AUTHORITY NOTE: Promulgated in accordance with Article VII, Part 2, Section 21(F) of the Louisiana Constitution of 1974.