Current through Register Vol. 43, No. 49, December 5, 2024
Section 82-17-4 - Reporting requirements(a) Each utility shall annually submit to the commission, by March 1, a report in a format approved by the commission listing all net metered facilities connected with the utility during the prior calendar year, pursuant to the act.(b) Each report shall specify the following information: (1) Information by customer type, including the following for each net metered facility: (A) The type of generation resource in operation;(B) zip code of the net metered facility;(C) first year of interconnection;(D) any excess kilowatt-hours that expired at the end of the prior calendar year;(F) number and type of meters; and(2) the utility's system retail peak in Kansas and total rated net metered generating capacity for all net metered facilities connected with the utility's system in Kansas. Kan. Admin. Regs. § 82-17-4
Authorized by K.S.A. 2009 Supp. 66-1269; implementing K.S.A. 2009 Supp. 66-1265, 66-1266, 66-1269, and 66-1271; effective Aug. 6, 2010.