Kan. Admin. Regs. § 82-12-5

Current through Register Vol. 43, No. 24, June 13, 2024
Section 82-12-5 - Notice of construction of electric supply lines

On or before the day a utility makes an application to the commission for any contemplated electric supply line construction, change in construction, or change in operating conditions to be located outside the corporate limits of any city, the utility shall send written notice of their plan:

(a) To the commission, at least 10 days before commencing construction;
(b) to railroads within 1/2 mile of the contemplated construction. The application shall not be considered for approval until at least 15 days after that notice is sent; and
(c) to all other utilities within 1/2 mile of the contemplated construction unless the utilities have executed a joint use or other agreement covering the area in which the construction is proposed. The application shall not be considered for approval until at least 10 days after this notice is sent.

Kan. Admin. Regs. § 82-12-5

Authorized by and implementing K.S.A. 66-183; effective Aug. 11, 1995.