Section 5-40-14 - Testing a principal spillway pipe installation in a dam; applicability
(a) For the purpose of testing the leakage rate of principal spillway pipe installation in a dam, an applicant shall conduct a static pressure test of each principal spillway installation constructed of corrugated metal pipe.
(b) A static pressure test shall be required only of a principal spillway installation made of corrugated metal pipe, unless the chief engineer determines that testing principal spillway pipe made of other materials or testing other pipes used in the construction of dams is necessary to protect public safety, life, or property.

Kan. Admin. Regs. § 5-40-14

Authorized by K.S.A. 82a-303a; implementing K.S.A. 82a-303b; effective Sept. 22, 2000.