Section 5-40-12 - As-built drawings
(a) Each permit shall be conditioned by the chief engineer to require as-built drawings for each category listed in subsection (b) to be submitted within 90 days of the completion of the dam, repairs, or modifications, or any extension of time authorized by the chief engineer for good cause. The drawings shall be prepared by a person qualified to prepare the original plans and specifications pursuant to K.A.R. 5-40-4.
(b) As-built drawings shall be submitted for each of the following categories:
(1) All high-impact dams;
(2) any dam, if required by the chief engineer as a condition of the permit to build, repair, or modify the dam; and
(3) any dam, if required by the chief engineer as the result of an approval of a change in the approved plans requested by the applicant during construction.
(c) The as-built drawings shall show all the features of the structure included in the approved plans as those features were constructed. A legibly marked-up copy of the approved plans shall be acceptable as as-built drawings.
(d) A profile of the bottom of the cutoff trench as constructed shall be shown on the as-built drawings.