Kan. Admin. Regs. § 28-16-60

Current through Register Vol. 43, No. 17, April 25, 2024
Section 28-16-60 - Development of draft permit
(a) Each application and any other relevant facts shall be reviewed by the director to determine one of the following:
(1) A permit shall be issued allowing the discharge.
(2) A permit shall be issued providing for no discharge.
(3) A permit shall not be issued.
(b) If the issuance of a permit is deemed advisable, the proposed permit conditions shall be formulated by the director, including all of the following:
(1) Effluent limitations developed according to the "Kansas implementation procedures: wastewater permitting";
(2) a schedule of compliance, including any necessary interim dates;
(3) any special conditions; and
(4) a monitoring program, if appropriate.

Kan. Admin. Regs. § 28-16-60

Authorized by K.S.A. 2000 Supp. 65-171d, as amended by L. 2001, Ch. 160, Sec. 15 and L. 2001, Ch. 191, Sec. 15; implementing K.S.A. 2000 Supp. 65-165 and K.S.A. 65-166; effective, E-74-32, June 14, 1974; effective May 1, 1975; amended May 1, 1987; amended Aug. 31, 2001.