Kan. Admin. Regs. § 28-16-134

Current through Register Vol. 43, No. 24, June 13, 2024
Section 28-16-134 - Projects documents
(a) Each loan applicant for a sewerage facility projects shall submit, for the secretary's review and approval, the following documents:
(1) A completed loan application on application forms furnished by the department;
(2) A facilities plan that establishes the need for the project;
(3) Complete design plans, specifications, and construction bidding documents, including detailed cost estimates necessary for competitive bidding, and projected construction and payment schedules;
(4) A plan of operation, including an overall project completion schedule, annual operating cost projections for a minimum of five years, a description of the financial management system, and projected revenues to operate and maintain the entire facility. Revenue projections shall also include the loan repayment obligations; and
(5) A facility operations manual, which shall be submitted before 90% of the project is completed.
(b) Each loan applicant for a nonpoint source pollution control management plan implementation or groundwater quality protection project shall submit, for the secretary's review and approval, the following documents:
(1) A completed loan application on application forms furnished by the department;
(2) Planning documents or any assessment which establishes the need for the project;
(3) Documents needed to plan the construction of the project.
(4) A plan of operation and maintenance to assure project performance for the design life of the project; and
(5) A binding assurance that adequate financial resources will be available for operation and maintenance of the project during the life of the project.

Kan. Admin. Regs. § 28-16-134

Authorized by and implementing K.S.A. 1988 Supp. 65-3323; effective May 29, 1989.