Section 11-3-7 - Notification of completion(a) The district shall notify the commission and the chief engineer when the district's approved project is complete and ready for final inspection. (b) The notification to the commission shall include the following: (1) The date of completion of the project; and (2) an itemized list of all costs of the following: (A) Construction or rehabilitation; and (B) engineering inspections and geological investigations. (c) The district shall submit a request for final payment of state funds for the project on a form provided by the commission, after the issuance of the certificate of completion by the chief engineer. Kan. Admin. Regs. § 11-3-7
Authorized by K.S.A. 2-1904, K.S.A. 2005 Supp. 2-1915, and L. 2005, ch. 206, sec. 75; implementing K.S.A. 2005 Supp. 2-1915 and L. 2005, ch. 206, sec. 75; effective, T-86-43, Dec. 18, 1985; effective May 1, 1986; amended March 24, 2006.