Cost categories shall be further described by the following subcategories: classifications of persons to be working on energy efficiency and demand response programs, full-time equivalents, dollar amounts of labor costs, and the name of outside firm(s) employed and a description of service(s) to be provided.
* Total system class maximum demand (in kW), number of customers in the class, and system class sales (in kWh);
* Jurisdictional class contribution (in kW) to the monthly maximum system coincident demand as allocated to jurisdiction;
* Total class contribution (in kW) to the monthly maximum system coincident demand, if not previously reported;
* Total system class maximum demand (in kW) allocated to jurisdiction, if not previously reported; and
* Hourly total system class loads for a typical weekday, a typical weekend day, the day of the class maximum demand, and the day of the system peak.
* Both summer and winter net generating capability ratings as reported to the North American Electric Reliability Corporation (NERC).
* The estimated remaining time before the unit will be retired or require life extension.
* The type of generating capacity.
* The anticipated in-service year of the capacity.
* The anticipated life of the generating capacity.
* Both summer and winter net generating capability ratings as reported to the NERC.
* The entity with whom commitments have been made and the time periods for each commitment.
* The capacity levels in each year for the commitment.
* The entity with whom a commitment has been made and the time periods for the commitment.
* The capacity levels in each year.
* The capacity payments to be received per kW per year in each year.
* The energy payments to be received per kWh per year.
* Any other payments the utility receives in each year.
* The anticipated year the supply option would be needed.
* The anticipated type of supply option, by fuel.
* The anticipated net capacity of the supply option.
* The anticipated life.
* The anticipated total capital costs per net kW, including allowance for funds used during construction (AFUDC) if applicable.
* The anticipated revenue requirement of the capital costs per net kW per year.
* The anticipated revenue requirement of the annual fixed operations and maintenance costs, including property taxes, per net kW for each year of the 20-year planning horizon.
* The anticipated net present value of the revenue requirements per net kW.
* The anticipated revenue requirement per net kW per year calculated by utilization of an economic carrying charge.
* The after-tax discount rate used to calculate the revenue requirement per net kW per year over the life of the supply option.
* Adjustment rates (for example, inflation or escalation rates) used to derive each future cost in numbered paragraph 35.5(4)"m"(6)"3."
* The anticipated annual cost per net kW per year of capacity purchases from numbered paragraph 35.5(4)"m"(6)"2" allocated to each costing period if it is the highest cost supply option in that year.
* The anticipated total revenue requirement per net kW per year from numbered paragraph 35.5(4)"m"(6)"3" allocated to each costing period if it is the highest cost supply option in that year.
AVOIDED CAPACITY COST = C × (1 + RM) × (1 + DLF) × (1 + EF)
C (capacity) is the greater of NC or RC.
NC (new capacity) is the value of future capacity purchase costs or future capacity costs expressed in dollars per net kW per year of the utility's new supply options from numbered paragraphs 35.5(4)"m"(6) "2" and "3" in each costing period.
RC (resalable capacity) is the value of existing capacity expressed in dollars per net kW per year that could be sold to other parties in each costing period.
RM (reserve margin) is the generation reserve margin criterion adopted by the utility.
DLF (demand loss factor) is the system demand loss factor expressed as a fraction of the net power generated, purchased, or interchanged in each costing period. For example, the peak system demand loss factor would be equal to peak system power loss (MW) divided by the net system peak load (MW) for each costing period.
EF (externality factor) is a 10 percent factor applied to avoided capacity costs in each costing period to account for societal costs of supplying energy. In addition, the utility may propose a different externality factor but must document the factor's accuracy.
AVOIDED ENERGY COSTS = MEC × (1 + ELF) × (1 + EF)
MEC (marginal energy cost) is the marginal energy cost expressed in dollars per kWh, inclusive of variable operations and maintenance costs, for electricity in each costing period.
ELF (system energy loss factor) is the system energy loss factor expressed as a fraction of net energy generated, purchased, or interchanged in each costing period.
EF (externality factor) is a 10 percent factor applied to avoided energy costs in each costing period to account for societal costs of supplying energy. In addition, the utility may propose a different externality factor but must submit documentation of the factor's accuracy.
AVOIDED CAPACITY COSTS = [(D + OC) × (1 + RM)] × (1 + EF)
D (demand) is the greater of CD or FD.
CD (current demand cost) is the utility's average demand cost expressed in dollars per dth or Mcf during peak and off-peak periods.
FD (future demand costs) is the utility's average future demand cost over the 20-year period expressed in dollars per dth or Mcf when supplying natural gas during peak and off-peak periods.
RM (reserve margin) is the reserve margin adopted by the utility.
OC (other cost) is the value of any other costs per dth or Mcf related to the acquisition of natural gas supply or transportation by the utility over the 20-year period in the peak and off-peak periods.
EF (externality factor) is a 7.5 percent factor applied to avoided capacity costs in the peak and off-peak periods to account for societal costs of supplying energy. In addition, the utility may propose a different externality factor but must submit documentation of the factor's accuracy.
AVOIDED ENERGY COSTS = (E + VOM) × (1 + EF)
E (energy costs) is the greater of ME or FE.
ME (current marginal energy costs) is the utility's current marginal energy costs expressed in dollars per dth or Mcf during peak and off-peak periods.
FE (future energy costs) is the utility's average future energy costs over the 20-year period expressed in dollars per dth or Mcf during peak and off-peak periods.
VOM (variable operations and maintenance costs) is the utility's average variable operations and maintenance costs over the 20-year period expressed in dollars per dth or Mcf during peak and off-peak periods.
EF (externality factor) is a 7.5 percent factor applied to avoided energy costs in the peak and off-peak periods to account for societal costs of supplying energy. In addition, the utility may propose a different externality factor but must submit documentation of the factor's accuracy.
Iowa Admin. Code r. 199-35.5