Section 80 IAC 9-4-9 - Commencement of warranty period

Authority: IC 15-13-2-9

Affected: IC 15-13-2

Sec. 9.

Each commission works contract must require that all warranty periods applying to work performed under the contract commence not later than the date that all work under the contract is substantially completed as determined by the commission.