Current through January 8, 2025
Section 80 IAC 9-4-3 - Projects costing less than $150,000; quotations from contractors; awardAuthority: IC 15-13-2-9
Affected: IC 5-16-1-3; IC 15-13-2
Sec. 3.
(a) If the estimated cost of a commission works project is less than one hundred fifty thousand dollars ($150,000), the executive director, in his or her discretion, may award a commission works contract either under: (1) section 2 of this rule; or(b) If the executive director awards a contract under this section, the commission shall: (1) publish notice in accordance with IC 5-16-1-3(a); or(2) require the invitation of quotations from at least three (3) contractors known to them to deal in the work required to be done in accordance with IC 5-16-1-3(b)(2). Failure to receive three (3) quotations shall not prevent an award from being made.
(c) Quotations given by a contractor under this section:(2) shall be considered firm; and(3) may be the basis upon which the executive director awards a commission works contract.(d) A contract shall be awarded to the lowest responsible and responsive contractor.(e) This subsection applies whenever a contract is awarded by quotation. A quote submitted by a trust (as defined in IC 30-4- 1-1(a)) must identify each of the following: (1) The beneficiary of the trust.(2) The settlor empowered to revoke or modify the trust.State Fair Commission; 80 IAC 9-4-3; filed 11/7/2016, 3:46 p.m.: 20161207-IR-080160210FRAReadopted filed 11/15/2022, 10:12 a.m.: 20221214-IR-080220291RFA