Current through January 8, 2025
Section 80 IAC 9-4-1 - Method of awarding contracts; approval of contract documentsAuthority: IC 15-13-2-9
Affected: IC 15-13-2
Sec. 1.
(a) Commission works contracts must be awarded under section 2 of this rule unless another method is authorized under this rule.(b) At the discretion of the commission or commission representative, a duly certified or registered architect or licensed engineer may be utilized to approve the contract documents for a commission works project. A consulting engineer or architect may be retained by the commission by a professional services contract for the purpose of assisting in the administration of the provisions of this article.State Fair Commission; 80 IAC 9-4-1; filed 11/7/2016, 3:46 p.m.: 20161207-IR-080160210FRAReadopted filed 11/15/2022, 10:12 a.m.: 20221214-IR-080220291RFA