675 Ind. Admin. Code 30-3-17

Current through October 23, 2024
Section 675 IAC 30-3-17 - Notice of violations; issuance of orders

Authority: IC 22-13-2-8

Affected: IC 4-21.5-3-6; IC 22-12-7; IC 22-15-6

Sec. 17.

If, upon the inspection of any boiler or unfired pressure vessel in service, it is found that the same does not fully conform to the standards prescribed in this article but the same is still deemed safe to continue operation the inspector or the employing inspection agency shall submit an inspection report documenting the violations to the division. Upon confirming the violations, the division shall issue an order as set forth at IC 22-12-7 and IC 4-21.5-3-6 granting a reasonable time in which to correct the violations.

675 IAC 30-3-17

Fire Prevention and Building Safety Commission; 675 IAC 30-3-17; filed Jan 5, 1996, 10:15 a.m.: 19 IR 1117; readopted filed Jul 9, 2001, 1:33 p.m.: 24 IR 3822; readopted filed Sep 21, 2007, 9:16 a.m.: 20071010-IR-680070389RFA; readopted filed Oct 19, 2007, 1:08 p.m.: 20071114-IR-680070389RFA; readopted filed Sep 5, 2013, 10:09 a.m.: 20131009-IR-680130182RFA; readopted filed 9/4/2019, 2:20 p.m.: 20191002-IR-675190336RFA
Filed 4/28/2021, 11:03 a.m.: 20210526-IR-675200627FRA, eff 7/1/2021

Transferred from the Boiler and Pressure Vessel Rules Board ( 680 IAC 2-3-17) to the Fire Prevention and Building Safety Commission ( 675 IAC 30-3-17) by P.L. 249-2019, SECTION 15, effective July 1, 2019.