Current through October 31, 2024
Section 675 IAC 13-2.6-21 - Chapter 19; concreteAuthority: IC 22-13-2-2; IC 22-13-2-13
Affected: IC 22-12; IC 22-13; IC 22-14; IC 22-15; IC 36-7
Sec. 21.
Chapter 19 is amended as follows:
(a) Amend Section 1901.3, Construction documents, by deleting the text and inserting to read as follows: See the General Administrative Rules ( 675 IAC 12-6 ) and the rules for Industrialized Building Systems ( 675 IAC 12-6 ).(b) Delete Section 1908.5, Increase for special inspections, without substitution.(c) Amend Section 1910.5, Preconstruction tests, by deleting "When required by the building official" and inserting "When required by the registered design professional".(d) Amend Section 1910.7, Joints, by deleting "approved".(e) Amend Section 1912.6, Approvals, by deleting the last sentence and inserting to read as follows: Shop-fabricated concrete-filled pipe columns shall be approved by the building official. Filed 8/1/2014, 11:12 a.m.: 20140827-IR-675130339FRA, eff 12/1/2014Readopted filed 8/6/2020, 2:04 p.m.: 20200902-IR-675200309RFA