410 Ind. Admin. Code 38-6-2

Current through December 25, 2024
Section 410 IAC 38-6-2 - Duties of a demolition contractor

Authority: IC 4-22-2; IC 16-19-3.1-1; IC 16-19-3.1-4; IC 35-48-4

Affected: IC 5-2-15; IC 16-19-3.1

Sec. 2.

The demolition contractor shall do all of the following:

(1) Review the Indiana State Police Methamphetamine Laboratory Occurrence Report prepared by the law enforcement agency under IC 5-2-15 for that property.
(2) Perform a visual inspection of the contaminated property to identify safety and health hazards at the property that can affect the health of persons at or near the property.
(3) Notify the local health department of the following:
(A) That demolition will be conducted at that location.
(B) The date that demolition will begin.
(4) Remove the septic tank or ensure the septic tank has been emptied. Notify the person who pumps out the septic system that the property was used for illegal manufacture of a controlled substance.
(5) Protect all persons at the contaminated property from hazards identified at that property, including respiratory protection if needed.
(6) Remove all soil that has been contaminated with chemicals used in the illegal manufacture of a controlled substance.
(7) Prevent salvaging of materials from the contaminated property or transfer of those materials to another person.
(8) Dispose of all materials resulting from activities under this rule in accordance with 329 IAC 10 no more than seventy-two (72) hours after demolition is completed.

410 IAC 38-6-2

Indiana State Department of Health; 410 IAC 38-6-2; filed Feb 21, 2007, 1:56 p.m.: 20070321-IR-318060125FRA; readopted filed Aug 5, 2013, 2:08 p.m.: 20130904-IR-318130240RFA; Readopted filed 11/13/2019, 3:14 p.m.: 20191211-IR-410190391RFA

Transferred from the Department of Environmental Management ( 318 IAC 1-6-2) to the Indiana State Department of Health ( 410 IAC 38-6-2) by P.L. 111-2018, SECTION 17, effective July 1, 2018.