355 Ind. Admin. Code 3-8-7

Current through January 8, 2025
Section 355 IAC 3-8-7 - Reinstallation of tanks; retesting

Authority: IC 15-16-1-6; IC 15-16-1-7

Affected: IC 15-16-1-1; IC 15-16-1-10

Sec. 7.

Tanks of such size as to require field fabrication shall be, when moved and reinstalled, reconstructed and reinspected in complete accordance with the code under which they were constructed. The tanks shall be subjected to a pressure retest, and, if rerating is necessary, the test shall be done in accordance with the applicable code procedures.

355 IAC 3-8-7

State Chemist of the State of Indiana; Agricultural Ammonia PT A, Sec VIII Rule 8.6; filed Dec 30, 1965, 2:15 p.m.: Rules and Regs. 1966 p. 23; filed Jan 19, 2001, 2:04 p.m.: 24 IR 1646; readopted filed Jun 20, 2001, 3:22 p.m.: 24 IR 3822; readopted filed Apr 27, 2007, 2:03 p.m.: 20070509-IR-355070039RFA; readopted filed November 25, 2013, 3:27 p.m.: 20131225-IR-355130482RFA
Readopted filed 7/2/2019, 10:42 a.m.: 20190731-IR-355190258RFA