329 Ind. Admin. Code 3.1-4-18

Current through September 18, 2024
Section 329 IAC 3.1-4-18 - "New tank system" or "new tank component" defined

Authority: IC 13-7-7; IC 13-7-8.5

Affected: IC 5-14-3-2

Sec. 18.

"New tank system" or "new tank component" means a tank system or component that will be used for storage or treatment of hazardous waste and for which installation commenced after June 20, 1988; however, for purposes of 40 CFR 264.193(g)(2) and 40 CFR 265.193(g)(2), a new tank system is one for which construction commenced after June 20, 1988.

329 IAC 3.1-4-18

Solid Waste Management Board; 329 IAC 3.1-4-18; filed Jan 24, 1992, 2:00 p.m.: 15 IR 922; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535