Section 329 IAC 11-12-2 - Preoperational requirements

Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1

Affected: IC 13-30-2; IC 36-9-30

Sec. 2.

Before beginning operation, a solid waste processing facility must complete the initial facility development outlined in the permitted plans and specifications. Initial facility development includes the following:

(1) Construction of buildings or structures and on-site roads.
(2) Installation of equipment for storage, processing, and handling of solid waste.
(3) Installation of the following:
(A) Access control.
(B) Sanitary facilities.
(C) Signs.
(D) Communication devices.
(E) Utilities.
(4) Financial assurance must be established under 329 IAC 11-16 for the solid waste processing facility.