Section 329 IAC 1-3-6 - Other penalty considerationsAuthority: IC 4-22-2; IC 13-14-9; IC 13-30-4-1
Affected: IC 13-30-4
Sec. 6.
(a) A negotiated order may contain a provision that allows a portion of the civil penalty to be offset by a qualified supplemental environmental project.(b) An order may include a stipulated or an additional penalty as follows: (1) An order may specify certain actions the violator must take to remediate an environmental problem or comply with a requirement.(2) The order must list the necessary actions and include: (A) a milestone date for each action; and(B) a stipulated or an additional penalty that is contingent on completion of the critical actions in a timely and satisfactory manner.(3) A stipulated or an additional penalty is separate from the assessed civil penalty.(4) A stipulated or an additional penalty is assessed in amounts that provide an incentive sufficient to meet the milestone.Solid Waste Management Division; 329 IAC 1-3-6; filed 11/18/2024, 5:00 p.m.: 20241218-IR-329240048FRA