327 Ind. Admin. Code 8-3.5-4

Current through October 2, 2024
Section 327 IAC 8-3.5-4 - Notice of intent letter

Authority: IC 13-14-8; IC 13-14-9; IC 13-15-2; IC 13-18-1; IC 13-18-3; IC 13-18-4; IC 13-18-16-8

Affected: IC 13-11-2; IC 13-18

Sec. 4.

(a) A responsible person who elects to participate in the General Construction Permit Program shall submit a NOI that complies with this section and is received by the commissioner at least thirty (30) calendar days before the commencement of construction of the proposed water main.
(b) A NOI must be submitted on forms obtained from the commissioner or a computer generated reproduction that is similar in appearance and identical in content to the forms generated by the commissioner.
(c) The NOI must be submitted by certified mail to the address provided on the NOI form.
(d) The NOI must include the following:
(1) The names, firms, addresses, and telephone numbers of the following:
(A) The responsible person.
(B) The responsible person's professional engineer.
(C) The responsible person's developer, resident project representative, or person who by other means is representing the construction aspects of the proposed project.
(2) The title of the proposed project for which the NOI is submitted.
(3) The name of the public water system and the corresponding public water system identification number, mailing address, and telephone number.
(4) The county and nearest public intersection and the nearest quarter section in which the construction project is located or, if the section, township, and range are not available, the latitude and longitude of the approximate center of the construction project to the nearest fifteen (15) seconds.
(5) A statement from the responsible person that indicates which one (1) of the following two (2) methods of construction activity notification the responsible person will comply with:
(A) The proposed construction schedule is included with the NOI.
(B) The proposed construction schedule will be submitted separate from the NOI at least ten (10) working days before the commencement of the construction and will include a copy of the information required in subdivisions (1) through (4).
(6) The certifications required in section 7 of this rule.
(7) A dated signature from the public water system certifying that the public water system will fulfill the requirements of section 12 of this rule.
(8) The average daily customer demand and the peaking factor of the proposed water main.
(9) The public water system's:
(A) daily capacity; and
(B) two (2) year average peak.
(10) Any fees as required by 327 IAC 8-3-7.
(11) A copy of any approvals from the commissioner of alternative technical standards that will apply to the proposed water main.
(12) A copy of any approvals from the commissioner of alternate average daily customer demand, peaking factor, or peak daily customer demand that will apply to the proposed water main.
(13) A copy of any written authorization of a duly authorized representative of a responsible person.

327 IAC 8-3.5-4

Water Pollution Control Board; 327 IAC 8-3.5-4; filed Mar 31, 1999, 10:20 a.m.: 22 IR 2523; errata filed Aug 17, 1999, 3:15 p.m.: 23 IR 26; readopted filed Jan 10, 2001, 3:23 p.m.: 24 IR 1518; readopted filed Nov 21, 2007, 1:16 p.m.: 20071219-IR-327070553BFA; readopted filed Jul 29, 2013, 9:21 a.m.: 20130828-IR-327130176BFA
Readopted filed Jun 6, 2019, 1:59 p.m.: 20190710-IR-327190246BFA