327 Ind. Admin. Code 5-21-3

Current through May 29, 2024
Section 327 IAC 5-21-3 - Permit application submission requirements

Authority: IC 13-14-8; IC 13-15-1-2; IC 13-15-2-1; IC 13-16; IC 13-18-2; IC 13-18-3

Affected: IC 13-11-2; IC 13-13-5-1; IC 13-18-4

Sec. 3

An application for an IWP permit must conform to the following:

(1) Be completed on a form prescribed by the commissioner.
(2) Be signed in accordance with 327 IAC 5-2-22(a).
(3) Be submitted to the commissioner according to the following time requirements:
(A) Not later than one hundred eighty (180) days prior to the expiration date of an existing permit if the industrial user intends to continue discharging to the POTW.
(B) Not later than one hundred eighty (180) days prior to the date when a new industrial discharger intends to commence discharging to a POTW.
(C) In the case of an initial issuance of an IWP permit to a significant industrial user or to an industrial user determined by the commissioner to be subject to the IWP permit requirements, not later than one hundred twenty (120) days after the latter of:
(i) the promulgation of an applicable categorical pretreatment standard; or
(ii) the date of notification by the commissioner of a determination made according to section 2(a)(2) of this rule. (D) Not later than one hundred twenty (120) days prior to a planned expansion or modification of production or treatment facilities or processes that are likely to cause a significant increase in quantity of pollutants or a change in the nature of pollutants discharged to the POTW by an industrial user with an existing IWP permit.
(4) Include the appropriate fee required under section 12 of this rule.

327 IAC 5-21-3

Water Pollution Control Board; 327 IAC 5-21-3; filed Oct 10, 2000, 3:02 p.m.: 24 IR 315
Filed 5/23/2022, 9:56 a.m.: 20220622-IR-327200026FRA