Authority: IC 13-14-8-7; IC 13-18-4-3
Affected: IC 13-18-3-1
Sec. 3.
Whenever, in the determination of the commissioner, a semipublic facility or POTW has reached or is approaching ninety percent (90%) of its hydraulic or organic design capacity, the commissioner shall notify the semipublic facility or POTW that it may be necessary, because of such condition, to impose a sewer connection ban if action is not taken by the semipublic facility or POTW to accommodate additional flow or loading. The notification shall be:
of the semipublic facility or POTW.
Failure of the commissioner to provide the notification to the semipublic facility or POTW shall not preclude the imposition of a sewer connection ban as authorized by this article.
327 IAC 4-1-3