327 Ind. Admin. Code 3-6-15

Current through November 6, 2024
Section 327 IAC 3-6-15 - Alignment requirements

Authority: IC 13-13-5; IC 13-14-8; IC 13-14-9; IC 13-15-1-2; IC 13-15-2-1; IC 13-18-2

Affected: IC 13-11-2; IC 13-15; IC 13-18

Sec. 15.

A sanitary sewer, between any two (2) manholes, shall be laid with straight alignment from the outlet centerline of the upstream pipe and the inlet centerline of the downstream pipe.

327 IAC 3-6-15

Water Pollution Control Board; 327 IAC 3-6-15; filed May 17, 1999, 12:11 p.m.: 22 IR 3093; readopted filed Apr 11, 2005, 2:45 p.m.: 28 IR 2470; readopted filed Jun 15, 2011, 11:15 a.m.: 20110713-IR-327110193BFA
Readopted filed Jun 29, 2017, 9:34 a.m.: 20170726-IR-327170225BFA
Readopted filed 5/12/2023, 1:07 p.m.: 20230607-IR-327230079BFA