Authority: IC 13-18-3-1; IC 13-18-22-1; IC 13-18-22-7
Affected: IC 13-18-3; IC 13-18-4; IC 14-34
Sec. 2.
The dredging may not be done primarily to obtain fill for any restoration activities. The discharge of dredged or fill material and all related work needed to restore the upland must be part of a single and complete project. This permit cannot be used in conjunction with subdivision (11) to restore damaged upland areas. This permit cannot be used to reclaim historic lands lost, over an extended period, to normal erosion processes. Any work authorized by this permit must not cause more than minimal degradation of water quality or increase flooding. A permit issued under this subdivision authorizes the repair, rehabilitation, or replacement of any previously authorized structure or fill that does not qualify for the 327 IAC 17-1-7(3)(B) exemption for maintenance.
The discharge of drilling mud and cuttings may require a permit under 327 IAC 5.
Activities authorized by clauses (A) through (C) may not exceed a total of one-half (1/2) acre loss of SRWs. SRWs temporarily affected by filling, flooding, excavation, or drainage, where the project area is restored to preconstruction contours and elevation, are not included in the calculation of permanent loss of SRWs. This includes temporary construction mats, for example, timber, steel, and geotextile, used during construction and removed upon completion of the work. Where certain functions and values of SRWs are permanently adversely affected, such as the conversion of a forested wetland to a herbaceous wetland in the permanently maintained utility line right-of-way, mitigation will be required to reduce the adverse effects of the project to the minimal level. Mechanized land clearing necessary for the construction, maintenance, or repair of utility lines and the construction, maintenance, and expansion of utility line substations, foundations for overhead utility lines, and access roads is authorized, provided the cleared area is kept to the minimum necessary and preconstruction contours are maintained as near as possible. The area of SRWs that is filled, excavated, or flooded must be limited to the minimum necessary to construct the utility line, substations, foundations, and access roads. Excess material must be removed to upland areas immediately upon completion of construction. Access roads used for both construction and maintenance may be authorized, provided they meet the terms and conditions of this rule. Access roads used solely for construction of the utility line must be removed upon completion of the work and the area restored to preconstruction contours, elevations, and wetland conditions.
Activities authorized by this subdivision include, to the extent that a permit is required under IC 13-18-22-1, the removal of accumulated sediments; the installation, removal, and maintenance of dikes and berms; the construction of small nesting islands; the construction of open water areas; activities needed to reestablish vegetation, including plowing or discing for seed bed preparation and the planting of appropriate wetland species; mechanized land clearing to remove nonnative invasive, exotic, or nuisance vegetation; and other related activities. This subdivision does not authorize the conversion of natural wetlands to another aquatic use, such as creation of waterfowl impoundments where a forested wetland previously existed. However, this subdivision authorizes the relocation of wetlands on the project site provided there are net gains in aquatic resource functions and values. For example, this subdivision may authorize the creation of an open water impoundment in an emergent wetland provided the emergent wetland is replaced by creating that wetland type on the project site. For enhancement, restoration, and creation projects conducted under item (iii), this subdivision does not authorize any future discharge of dredged or fill material associated with the reversion of the area to its prior condition. In such cases, a separate permit would be required for any reversion if not otherwise exempt under this article. For restoration, enhancement, and creation projects conducted under items (i) and (ii), this subdivision also authorizes any future discharge of dredged or fill material associated with the reversion of the area to its documented prior condition and use, that is, prior to the restoration, enhancement, or creation activities if a permit is otherwise required under this article for such reversion activities. The reversion must occur within five (5) years after expiration of a limited term wetland restoration or creation agreement or permit, even if the discharge occurs after a permit issued under this subdivision expires. This subdivision also authorizes the reversion of wetlands that were restored, enhanced, or created on prior-converted cropland that has not been abandoned, in accordance with a binding agreement between the landowner and NRCS or FWS (even though the restoration, enhancement, or creation activity did not require an IC 13-18-22-1 permit). The five-year reversion limit does not apply to agreements without time limits reached under item (i). The prior condition will be documented in the original agreement or permit, and the determination of return to prior conditions will be made by the federal agency or appropriate state agency executing the agreement or permit. Before any reversion activity, the permittee or the appropriate federal or state agency must notify the commissioner and include the documentation of the prior condition. Once an area has reverted to its prior physical condition, it will be subject to whatever regulatory requirements are applicable at that future date.
Sufficient vegetated buffers must be maintained adjacent to all open waterbodies, streams, et cetera, to preclude water quality degradation due to erosion and sedimentation. This subdivision does not authorize the construction of new dikes, roads, water control structures, et cetera, associated with the management areas. This subdivision does not authorize converting wetlands to uplands, impoundments, or other open waterbodies.
or both, regardless of whether or not the discharge meets the area limitation specified in clause (C).
327 IAC 17-2-2