326 Ind. Admin. Code 8-7-6

Current through May 29, 2024
Section 326 IAC 8-7-6 - Certification, record keeping, and reporting requirements for coating facilities

Authority: IC 13-1-1-4; IC 13-7-7-5

Affected: IC 13-1-1; IC 13-7

Sec. 6.

On or before December 31, 1994, or upon the startup of any new coating facility meeting the aggregate potential emissions criteria of section 2(c) of this rule, each source or facility shall submit to the department a certification that the facility is exempt from the requirements of section 3 of this rule. The certification shall contain all of the following information:

(1) The name and address of the source and the name and telephone number of the company representative.
(2) Identification of each VOC emitting facility together with a description of the purpose each facility serves.
(3) A listing of facilities which meet the requirements of section 2(a) of this rule.
(4) Baseline actual emissions for each facility identified in subdivision (3) together with the following information:
(A) Maximum design rate, maximum production, or maximum throughput.
(B) VOC emission factors with reference to the source of the emission factors and procedures as to how the emission factors were estimated, for example, the type of each fuel or process chemicals used and the baseline year used.
(5) Procedures that will be used to monitor the source's potential emissions to ensure that they remain below twenty-five (25) tpy.

326 IAC 8-7-6

Air Pollution Control Board; 326 IAC 8-7-6; filed Dec 22, 1994, 11:45 a.m.: 18 IR 1227