Section 312 IAC 29-20-9 - Cement job log

Authority: IC 14-10-2-4; IC 14-37-3

Affected: IC 14-37

Sec. 9.

(a) An owner or operator shall maintain a copy of the cement job log at the well site and available for inspection by the division during drilling operations. The cement job log must include the following:
(1) The type of cement listing the type and amount of any additive.
(2) The volume.
(3) Yield and density in pounds per gallon of the cement.
(4) The amount of cement returned to the surface, if any.
(5) Cementing procedural information must include:
(A) a description of the pumping rates in barrels per minute;
(B) pressures in pounds per square inch;
(C) duration in minutes; and
(D) sequence of events during the cementing operation.
(b) An owner or operator shall submit a copy of the cement job log to the division with the well completion report as required by section 14 of this rule.