312 Ind. Admin. Code 29-10-4

Current through May 29, 2024
Section 312 IAC 29-10-4 - Post testing schedule

Authority: IC 14-10-2-4; IC 14-37-3

Affected: IC 14-37

Sec. 4.

The application shall include a schedule for the following:

(1) The length of time necessary for conducting the testing operations.
(2) Actions to be taken upon conclusion of the testing operations and the timing of either:
(A) converting the well to a production well or a Class II well; or
(B) plugging and abandoning the well.

312 IAC 29-10-4

Natural Resources Commission; 312 IAC 29-10-4; filed 12/1/2017, 10:35 a.m.: 20171227-IR-312160230FRA
Readopted filed 1/17/2023, 1:53 p.m.: 20230215-IR-312220328RFA