312 Ind. Admin. Code 25-9-4

Current through May 29, 2024
Section 312 IAC 25-9-4 - Application for certification

Authority: IC 14-34-2-1; IC 14-34-12-2

Affected: IC 14-34-12-1

Sec. 4.

(a) An application for certification as a certified blaster shall be submitted to the department.
(b) An application for certification shall be, in writing, on forms furnished by the department.
(c) An application shall be completed in accordance with the instructions provided with the application.
(d) An application form is incomplete if the form does not contain all required information or if the form contains incorrect information. The applicant will be given notice of the deficiencies, and, if the required information is not provided by the applicant within thirty (30) days of the notice, the application will be terminated.
(e) The director or an authorized representative may verify the information shown on the application directly with educational institutions, other certification boards, and personal references, and may verify the work experience with the employer.
(f) If an application has been terminated, the person will not be considered for certification. A new application may be submitted at any time by complying with subsections (b) and (c).

312 IAC 25-9-4

Natural Resources Commission; 312 IAC 25-9-4; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3608, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFA
Readopted filed 3/26/2019, 3:40 p.m.: 20190424-IR-312190011RFA