Sec. 4.

(a) In a case where the bidder has arranged to subcontract one hundred percent (100%) or more of the subcontractor goal to MBEs and WBEs, a completed MBE/WBE subcontractor plan shall be submitted along with the other required bid documents.
(1) All MBE and WBE subcontractors must be validated by the department prior to the award of the contract. The completed plan shall include the following information:
(A) Name of the enterprise to be employed.
(B) Phone number of the enterprise.
(C) Name of a contact person from the enterprise.
(D) Work the enterprise will perform and the approximate date when the MBEs work will commence.
(E) Contract amount for services that will be performed.
(2) In a case where the bidder has had the MBE/WBE subcontractor plan approved, where that bidder has been awarded the contract, and where the awarded contract is one hundred thousand dollars ($100,000) or more, the bidder shall submit participation reports monthly, or at more frequent intervals, as may be requested.
(3) The department reserves the right to periodically require progress reports from the contractor on projects less than one hundred thousand dollars ($100,000) regarding continuing MBE and WBE participation.
(b) Purchases from MBE or WBE suppliers are allowed for MBE or WBE credit in the program. The maximum allowable credit will be limited to sixty percent (60%) of the total project goal. The supplier must perform a commercially useful function.
(c) In a case where the bidder has been unable to arrange to subcontract one hundred percent (100%) of the subcontract goal, but has been able to arrange to subcontract some of the goal to MBEs or WBEs, both a completed MBE/WBE subcontractor plan and a completed application for MBE/WBE program waiver shall be submitted with the other required bid documents, as prescribed. All MBE and WBE subcontractors must be validated by the department prior to the award of the contract. All forms are to be completed as described in subsection (a).
(d) In a case where the bidder has been unable to arrange to subcontract the goal percentage or in a case where no MBE or WBE participation is expected to occur, a completed application for MBE/WBE program waiver shall be submitted, along with the other required bid documents, as prescribed. The application for program waiver shall be used to demonstrate the bidder's efforts to employ MBEs and WBEs on the project. The application shall include the following information:
(1) Names of the MBE and WBE enterprises that the bidder has contacted or been contacted by.
(2) Persons working at the enterprises who were contacted.
(3) Phone numbers of the enterprises.
(4) Types of contacts or communications.
(5) An explanation of the results obtained, such as price not competitive, unable to contact, or no response.

The state reserves the right to verify and seek further clarification of any information submitted.

(e) Compliance with this rule is considered to be a demonstration of the bidder's responsiveness and responsibility. Therefore, all statements shall be complete, legible, true, and correct and shall not omit material facts. Failure to provide complete and accurate MBE and WBE subcontractor plans using minority and women's business enterprises validated as MBEs and WBEs by the department or failure to provide applications for MBE/WBE program waivers, or both, may be the basis for rejection of the bid.

25 IAC 5-6-4

Indiana Department of Administration; 25 IAC 5-6-4; filed May 30, 2003, 11:00 a.m.: 26 IR 3308; readopted filed Oct 6, 2009, 9:04 a.m.: 20091104-IR-025090572RFA
Readopted filed 12/2/2015, 2:41 p.m.: 20151230-IR-025150342RFA
Readopted filed 10/19/2021, 9:13 a.m.: 20211117-IR-025210389RFA