25 Ind. Admin. Code 2-7-4

Current through October 31, 2024
Section 25 IAC 2-7-4 - Contract letter; documents required to initiate work

Authority: IC 4-13-2-9; IC 4-13.6-3-1

Affected: IC 4-13.6

Sec. 4.

The Contract shall be transmitted to the Contractor for his execution by a letter stating that the Contractor unless otherwise instructed in writing, should not commence any work or take delivery of noninventory materials until he receives a copy of the fully executed contract signed by all required signatories and all auxiliary documents including but not limited to insurance and bonds are completed and furnished to the state.

25 IAC 2-7-4

Indiana Department of Administration; Public Works Division Sec G,4; filed Feb 29, 1972, 4:10 pm: Rules and Regs. 1973, p.6; filed Feb 3, 1982, 1:05 pm: 5 IR 513; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; readopted filed Aug 26, 2008, 8:31 a.m.: 20080910-IR-025080549RFA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFA
Readopted filed 11/4/2019, 3:40 p.m.: 20191204-IR-025190494RFA