170 Ind. Admin. Code 6-3-17

Current through October 23, 2024
Section 170 IAC 6-3-17 - Underset radiation; rate increase

Authority: IC 8-1-1-3; IC 8-1-2-4

Affected: IC 8-1-2-32; IC 8-1-2-33; IC 8-1-2-39

Sec. 17.

Underset Radiation. Consumers having less than the proper amount of radiation installed shall be billed at the following increased rate until such time as they can procure and install the proper amount of radiation. Rates for direct radiation, where less than normal or standard amount of radiation is installed:

90% of normal or standard radiation installed, add 5% to normal rate.

80% of normal or standard radiation installed, add 10% to normal rate.

70% of normal or standard radiation installed, add 15% to normal rate.

60% of normal or standard radiation installed, add 20% to normal rate.

50% of normal or standard radiation installed, add 25% to normal rate.

Note.-By normal or standard amount of radiation is meant the radiator area required to keep the room or building at 70° F. inside when the outside temperature is zero in calm weather.

170 IAC 6-3-17

Indiana Utility Regulatory Commission; No. 17689: Standards of Service For Central Station Hot Water Heating Utilities Sec 17; filed Jan 2, 1946, 10:00 am: Rules and Regs. 1947, p. 1662; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA
Readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFA