Current through November 6, 2024
Section 170 IAC 4-3-7 - Existing construction; coordination of methodsAuthority: IC 8-1-1-3; IC 8-1-2-10
Affected: IC 8-1-2-5; IC 8-1-14-1; IC 8-3-1-1
Sec. 7.
Co-ordination for Existing Construction.
(a) Utilities operating supply or signal circuits should exercise due diligence in applying co-ordinated methods, as occasion may arise, in accordance with these principles, to existing construction.(b) When supply or signal circuits are generally reconstructed, or when associated apparatus is rearranged or added, or when any change is made in the arrangement or characteristics of circuits, the new or changed parts should be brought into conformity with these principles.Indiana Utility Regulatory Commission; No. 17689: Safety And Inductive Co-ordination Rule 7; filed Jan 2, 1946, 10:00 am: Rules and Regs. 1947, p. 1635; readopted filed Jul 11, 2001, 4:30 p.m.: 24 IR 4233; readopted filed Apr 24, 2007, 8:21 a.m.: 20070509-IR-170070147RFA; readopted filed Aug 2, 2013, 2:16 p.m.: 20130828-IR-170130227RFAReadopted filed 4/11/2019, 9:04 a.m.: 20190508-IR-170190136RFA