170 Ind. Admin. Code 4-11-2

Current through December 4, 2024
Section 170 IAC 4-11-2 - Applicability under IC 8-1-8.5-12.1

Authority: IC 8-1-1-3; IC 8-1-8.5-12.1

Affected: IC 8-1-8.5-1; IC 8-1-8.5-12.1; IC 8-1-8.8

Sec. 2.

This rule applies to a public utility, as defined under IC 8-1-8.5-1(a), petitioning the commission for approval of the construction, purchase, or lease of an SMR to provide utility service to Indiana customers.

170 IAC 4-11-2

Indiana Utility Regulatory Commission; 170 IAC 4-11-2; emergency rule filed 6/15/2023, 10:24 a.m.: 20230628-IR-170230500ERA (EMERGENCY)
Filed 8/6/2024, 12:23 p.m.: 20240904-IR-170240091FRA