Section 285.2055 - Schedule B-7: Construction Work in Progress
a) Provide information required by subsection (b) for each construction project included in Construction Work in Progress (CWIP) for the test year rate base that exceeds 5% of the total CWIP balance for the test year. If the CWIP project is not in rate base, the information is not required.
b) Information provided shall include:
1) Project number;
2) Description of project;
3) Direct costs of construction through the end of the test year;
4) Allowance for funds used during construction (AFUDC) or interest during construction (IDC) for telecommunications carriers capitalized through the end of the test year;
5) Other indirect costs through the end of the test year;
6) Total cost of construction project through the end of the test year; and
7) Amount included in the test year jurisdictional rate base.