Section 8.8092 - Effect on Current Contracts

Current CDB contracts may be terminated when a contractor is determined to be non-responsible and it is in the public interest to do so, whether or not the non-responsibility has a direct connection with the current contract. Contracts may be terminated with or without further action on the vendor's prequalification.

Ill. Admin. Code tit. 44, § 8.8092

Adopted at 38 Ill. Reg. 10903, effective 5/7/2014.