Ill. Admin. Code tit. 44 § 8.3120

Current through Register Vol. 48, No. 45, November 8, 2024
Section 8.3120 - Small Projects
a) For contracts whose estimated value is less than $25,000, CDB may select any prequalified A/E in accordance with Section 45 of the QBS Act.
b) For contracts whose value is less than $25,000, CDB may select any prequalified CM in accordance with Section 33-35 of the Code.
c) In any case in which the total overall cost of the project is estimated to be less than $10 million, CDB may combine the two-phase procedure for Design-Build submittals into one combined step, provided that all the requirements of evaluation are performed in accordance with this Part.

Ill. Admin. Code tit. 44, § 8.3120

Adopted at 38 Ill. Reg. 10903, effective 5/7/2014.