Section 215.526 - Testing and Monitoring
a) Upon request by the Agency during the permitting process under Section 39 of the Act, the owner or operator of an air oxidation process shall demonstrate compliance with this Subpart by use of the methods specified in Appendix E. This Section does not limit the USEPA's authority, under the Clear Air Act, to require demonstrations of compliance.
b) A person planning to conduct a volatile organic material emissions test to demonstrate compliance with this Subpart shall notify the Agency of that intent not less than 30 days before the planned initiation of the tests so that the Agency may observe the test.

Ill. Admin. Code tit. 35, § 215.526

Added at 11 Ill. Reg. 20829, effective December 14, 1987