Section 215.485 - Leaks

The owner or operator of a pharmaceutical manufacturing plant shall repair any component from which a leak of volatile organic liquid can be observed. The repair shall be completed as soon as practicable but no later than 15 days after the leak is found. If the leaking component cannot be repaired until the process unit is shut down, the leaking component must then be repaired before the unit is restarted.

Ill. Admin. Code tit. 35, § 215.485

Added at 12 Ill. Reg. 7650, effective April 11, 1988