Ill. Admin. Code tit. 35 § 201.243

Current through Register Vol. 48, No. 24, June 14, 2024
Section 201.243 - Standards for Approval

No compliance program and project completion schedule shall be approved unless the applicant submits proof to the Agency that:

a) The compliance program will result in timely compliance with the applicable standards and limitations of Subchapter c of this Chapter; and
b) The owner or operator has provided adequate proof that it is committed to the compliance program or project completion schedule, including, in the case of a corporation, certification by a duly authorized officer of such corporation that such corporation approves each and every provision of such program and of such schedule.

Ill. Admin. Code tit. 35, § 201.243