Ill. Admin. Code tit. 35 § 105.210

Current through Register Vol. 48, No. 24, June 14, 2024
Section 105.210 - Petition Content Requirements

In addition to the requirements of 35 Ill. Adm. Code 101. Subpart C, the petition must include:

a) The Agency's final decision or issued permit;
b) A statement specifying the date of issuance or service of the Agency's final decision or issued permit, as applicable under Section 105.206;
c) A statement specifying the grounds of appeal; and
d) For petitions under Section 105.204(b), a demonstration that the petitioner raised the issues contained within the petition during the public notice period or during the Agency public hearing on the NPDES permit application, if an Agency public hearing was held, and a demonstration that the petitioner is so situated as to be affected by the permitted facility. [415 ILCS 5/40(e)(2)]

Ill. Admin. Code tit. 35, § 105.210

Amended at 41 Ill. Reg. 10084, effective 7/5/2017
Amended at 44 Ill. Reg. 14897, effective 9/4/2020