Idaho Admin. Code r. 58.01.01.796

Current through August 31, 2023
Section 58.01.01.796 - APPLICABILITY
01.Permit by Rule. Owners and operators of nonmetallic mineral processing plants are deemed to have a permit by rule if they comply with all of the applicable provisions of Sections 795 through 799. Nothing in Sections 795 through 799 precludes any owner or operator from obtaining a permit. Portable sources that operate or may be operated at a single location or site of operations for more than twelve (12) consecutive months must obtain a permit to construct. (3-28-23)
02.Permit Option. Owners and operators of nonmetallic mineral processing plants that hold a valid permit to construct or a Tier II operating permit must comply with the terms and conditions of the permit and are not subject to the requirements of the permit by rule in Sections 795 through 799. (3-28-23)

Idaho Admin. Code r. 58.01.01.796