Idaho Admin. Code r. 58.01.01.381

Current through August 31, 2023
Section 58.01.01.381 - ADMINISTRATIVE PERMIT AMENDMENTS
01.Criteria. An administrative permit amendment is a permit revision that: (3-28-23)
a. Corrects typographical errors; (3-28-23)
b. Identifies a change in the name, address, or phone number of any person identified in the Tier I operating permit, or provides a similar minor administrative change at the Tier I source; (3-28-23)
c. Requires more frequent monitoring or reporting by the permittee; (3-28-23)
d. Allows for a change in ownership or operational control of a Tier I source where the Department determines that no other change in the Tier I operating permit is necessary, provided that a written agreement containing a specific date for transfer of permit responsibility, coverage, and liability between the current and new permittee has been submitted to the Department; (3-28-23)
e. Incorporates into the Tier I operating permit the requirements from a permit to construct that was issued by the Department in accordance with Subsection 209.05.c.; or (3-28-23)
f. Is any other type of change that EPA and the Department have determined as part of the Part 70 program to be similar to those in Subsections 381.01.a. through 381.01.d. (3-28-23)
02.Administrative Permit Amendment Application Procedures. (3-28-23)
a. If initiated by the permittee, the permittee must submit a request to the Department that: (3-28-23)
i. States at the beginning of the request that it is a "REQUEST FOR ADMINISTRATIVE PERMIT AMENDMENT." (3-28-23)
ii. Describes the proposed administrative permit amendment including any permit to construct to be incorporated; (3-28-23)
iii. States the date on which the proposed administrative amendment will occur at the facility; (3-28-23)
iv. Identifies any Tier I operating permit term or condition that is no longer applicable as a result of the change; and (3-28-23)
v. Identifies any applicable requirement that would apply to the Tier I source as a result of the change. (3-28-23)
b. If initiated by the Department, the Department will notify the permittee that the Department is initiating an administrative permit amendment and provide a brief summary of the proposed administrative permit amendment including all of the information required by Subsection 381.02.a.i. through 381.02.a.v. (3-28-23)
c. The Department will, within sixty (60) days of the receipt of a request for an administrative permit amendment, take final action on the request and may incorporate such changes without providing notice to the public or affected States provided that the Department designates any such administrative permit amendment as having been made pursuant to Section 381. The Department will submit a copy of the revised permit, or an addendum, to the EPA and send the original to the permittee. (3-28-23)
03.Implementation Procedures. (3-28-23)
a. The permittee may implement the changes addressed in the request for an administrative permit amendment under Subsections 381.01.a. through 381.01.f. immediately upon submittal of the request. (3-28-23)
b. If the permittee obtains a permit to construct under Subsection 209.05.c., then so long as the change does not violate any terms or conditions of the existing Tier I operating permit, the permittee may operate the source described in the permit to construct immediately upon submittal of the request for an administrative permit amendment. (3-28-23)
04.Permit Shield. Upon final action by the Department, the permit shield described in Section 325 extends only to administrative permit amendments identified in Subsection 381.01.e. (3-28-23)

Idaho Admin. Code r. 58.01.01.381