Section 39.03.01.316 - BRIDGE ANALYSIS CRITERIA AND TIME FRAMES
01.Timelines. The Department may take up to three (3) business days for an analysis on a vehicle or vehicle combination not in excess of two hundred fifty thousand (250,000) pounds and up to ten (10) business days for an analysis on a vehicle or vehicle combination over two hundred fifty thousand (250,000) pounds. Up to ten (10) business days will also be used for the review process of an analysis done by a third party. The following criteria will be used to determine bridge analysis work and whether it is to be completed by the Department or a qualified and pre-approved third party. If a third party is required, the applicant is responsible for finding, initiating and paying for the cost of that analysis.
02.Vehicle Combinations in Excess of Eight Hundred Thousand (800,000) Pounds. Vehicle combinations in excess of eight hundred thousand (800,000) pounds will be required to have a third party complete the bridge analysis. The analysis will then be reviewed by the Department for final approval or denial.
03.Preliminary Information or Bid Work. When a permit request is placed and paid for, the Department will complete the analysis, otherwise a third party will be required to complete the bridge analysis. An analysis completed by a third party may be used when a permit request is made, and it will be reviewed by the Department for final approval or denial.
04.Overweight Permit Requests with Multiple Configurations. Requests made to analyze multiple vehicle configurations for a specific route to determine which vehicle combination will be approved requires the analysis to be completed by a third party. The analysis will then be reviewed by the Department for final approval or denial.
05.Overweight Permit Requests with Multiple Routes. Requests made to analyze multiple routes for a specific vehicle combination in order to determine which route will be approved requires the analysis to be completed by a third party. The analysis will then be reviewed by the Department for final approval or denial.
06.Extenuating Circumstances. The Department may under extenuating circumstances require that a bridge analysis be completed by a third party.