Section 04.11.01.056 - COMPUTATION OF TIME

Whenever statute, these or other rules, order, or notice requires an act to be done within a certain number of days of a given day, the given day is not included in the count, but the last day of the period so computed is included in the count. If the day the act must be done is Saturday, Sunday or a legal holiday, the act may be done on the first day following that is not a Saturday, Sunday or a legal holiday. (3-31-22)