Section 3-123-4 - Allocable costs
(a) A cost is allocable if it is assignable or chargeable to one or more cost objectives in accordance with relative benefits received and if it:
(1) Is incurred specifically for the contract;
(2) Benefits both the contract and other work, and can be distributed to both in reasonable proportion to the benefits received; or
(3) Is necessary to the overall operation of the business, although a direct relationship to any particular cost objective may not be evident.
(b) Costs are allocable as direct or indirect costs. Similar costs such as those incurred for the same purpose, in like circumstances, shall be treated consistently either as direct costs or indirect costs except as provided by these rules. When a cost is treated as a direct cost in respect to one cost objective, it and all similar costs shall be treated as a direct cost for all cost objectives. Further, all costs similar to those included in any indirect cost pool shall be treated as indirect costs. All distributions to cost objectives from a cost pool shall be on the same basis.
(c) A direct cost is any cost which can be identified specifically with a particular final cost objective. A direct cost shall be allocated only to its specific cost objective. To be allowable, a direct cost must be incurred in accordance with the terms of the contract.
(d) An indirect cost is one identified with no specific final cost objective or with more than one final cost objective. Indirect costs are those remaining to be allocated to the several final cost objectives after direct costs have been determined and charged directly to the contract or other work as appropriate. Any direct costs of minor dollar amount may be treated as indirect costs, provided that such treatment produces substantially the same results as treating the cost as a direct cost.
(1) Indirect costs shall be accumulated into logical cost groups with consideration of the reasons for incurring the costs. Each group should be distributed to cost objectives benefiting from the costs in the group. Each indirect cost group shall be distributed to the cost objectives substantially in proportion to the benefits received by the cost objectives. The number and composition of the groups and the method of distribution should not unduly complicate indirect cost allocation where substantially the same results could be achieved through less precise methods.
(2) The contractor's method of indirect cost group distribution may require examination when:
(A) Any substantial difference exists between the cost patterns of the work performed under the contract and the contractor's other work;
(B) Any significant change occurs in the nature of the business, the extent of subcontracting, fixed asset improvement programs, inventories, the volume of sales and production, manufacturing processes, the contractor's products, or other relevant circumstances; or
(C) Indirect cost groups developed for a contractor's primary location are applied to off-site locations. Separate cost groups for costs allocable to off-site locations may be necessary to distribute the contractor's costs on the basis of the benefits accruing to the appropriate cost objectives.
(3) The base period for indirect cost allocation is the one in which such costs are incurred and accumulated for distribution to work performed in that period. Normally, the base period is the contractor's fiscal year. A different base period may be appropriate under unusual circumstances. In such cases, an appropriate period should be agreed to in advance.