Haw. Code R. § 15-22-23

Current through April, 2024
Section 15-22-23 - Automatic approvals
(a) The following development-related permits and approvals shall be deemed approved if no decisions are made granting or denying them within the following review periods:
(1) Master plan permits: 200 days;
(2) Planned development permits: 160 days;
(3) Base zone development permits: 160 days;
(4) Certificates of appropriateness: 160 days;
(5) Conditional use permits for off-site parking or joint use of parking: 160 days;
(6) Variances: 100 days;
(7) Modifications: 100 days;
(8) Certificates of project eligibility: 60 days;
(9) Conditional use permits for vacant land: 30 days;
(10) Zoning adjustments and waivers: 30 days; and
(11) Temporary use permits: 10 days.
(b) The review period shall commence upon submission of a complete application. In the event that no decision is rendered on the application within ten (10) days of the submission of a complete application, the applicant shall be notified of the date for automatic approval.
(c) When a proposed project requires more than one permit and/or approval listed in subsection (a) of this section, the applicant may apply for some or all such approvals concurrently. The review period for concurrent applications shall be based on the permit or approval with the longest review period.
(d) Application filing procedures and preparation guidelines may be provided to assist applicants.

Haw. Code R. § 15-22-23

[Eff 1/13/00] (Auth: HRS §§ 206E-4, 206E-5, 206E-7) (Imp: HRS §§ 206E-4, 206E-5, 206E-7)