Current through September, 2024
Section 15-219-100 - Time period for compliance(a) When determining the corrective action to be taken and a reasonable deadline to correct the violation, the executive director shall use the following schedule as a guide: Schedule for Correction of Violations
Type of Violation | Initial Violation | Repeated Violation |
Land Use | 15 days | 7 days or less |
Development Standard | 30 days | 15 days or less |
Permit Condition | 30 days | 15 days or less |
(b) This schedule is only a guide and may be modified in consideration of the following: (1) The type and the degree of the violation, whether it is a repeated violation, and the number of violations cited in the citation;(2) Whether the violation poses a threat or potential threat to human health and safety;(3) Procedural requirements for obtaining a permit or authorization to carry out corrective action;(4) The complexity of the corrective action required, including construction requirements and the legal prerogatives of landlords and tenants; and(5) Any other circumstances beyond the control of the violator. Haw. Code R. § 15-219-100
[Eff MAR 02 2012 ] (Auth: HRS §§ 91-2, 206E-4, 206E-22) (Imp: HRS §§ 206E-5, 206E-7, 206E-22)