Haw. Code R. § 13-190.1-16

Current through April, 2024
Section 13-190.1-16 - Transferability

Certificates of approval to impound water are not transferable from one person to another without written approval from the board; and:

(1) The existing holder of the certificate to impound requests a transfer in writing to the department; and
(2) The new or prospective dam owner submits in writing to the department:
(A) Proof that the person is or will become the owner of the dam;
(B) The date of change in ownership; and
(C) An acknowledgment of receipt of a copy of the certificate of approval to impound that is in effect, and of the person's awareness of the terms, including and without limitation, any conditions or restrictions on the operation imposed by the department.

Haw. Code R. § 13-190.1-16

[Eff. FEB 20 2012] (Auth: HRS § 179D-6)(Imp: HRS §§ 179D-6, 179D-21)