Haw. Code R. § 12-223.1-14

Current through September, 2024
Section 12-223.1-14 - Preventive maintenance schedule

Maintenance. The owner or user of the pressure retaining item is responsible for ensuring that all equipment is maintained as listed in this section. Steam boiler maintenance shall be performed as per ASME BPVC Section VI, Steam Boiler - Sec 7.7 Maintenance, and ASME CSD-1, Part CM (see Exhibit 1, titled, "Recommended Preventative Maintenance Schedule", dated October 1, 2023, which is made a part of this chapter and located at the end of this chapter, and Exhibit 2, titled, "Table D-1-1 Periodic Testing Recommended Checklist", dated October 1, 2023, which is made a part of this chapter and located at the end of this chapter). Hot-water boiler and hot-water heating boiler maintenance shall be performed as per ASME BPVC Section VI, Hot-Water Boiler and Hot-Water Heating Boiler - Sec 8.7 Maintenance, and Exhibit 1, titled, "Recommended Preventative Maintenance Schedule", dated October 1, 2023, which is made a part of this chapter and located at the end of this chapter, and Exhibit 2, titled, "Table D-1-1 Periodic Testing Recommended Checklist", dated October 1, 2023, which is made a part of this chapter and located at the end of this chapter.

Haw. Code R. § 12-223.1-14

[Eff and comp 12/21/2019] (Auth: HRS § 397-4) (Imp: HRS § 397-4)
Am and comp 9/8/2024